Study tips13 min read

QCE General Mathematics external exam: Paper 1 and Paper 2 questions worked through

Explore how each paper is set and marked, work through three exam-style questions mark by mark, and try five more with full answers.

Medly Team18 November 2026
On this page

The QCE General Mathematics external exam is worth 50% of your subject result. It has two papers: Paper 1 is made up of simple familiar questions, and Paper 2 of complex familiar and complex unfamiliar ones. Each paper gives you 90 minutes of working time plus 5 minutes of perusal, and you can use a QCAA-approved scientific calculator and the QCAA formula book. Below, three exam-style questions are worked through mark by mark, one each from regression, loans and networks, followed by five more for you to try.

How Paper 1 and Paper 2 differ in the General Mathematics external exam

Under the 2025 syllabus, both papers assess Units 3 and 4. What changes between them is the kind of question.

Simple familiar questions look like the ones you practised in class. The method is clear from the wording, and most are worth a few marks. Complex familiar questions chain several methods you know, with less signposting. Complex unfamiliar questions put the maths in a setting you haven't met and often ask you to evaluate or justify, so a mark usually rides on a conclusion that refers back to the context.

PaperQuestionsWeightingTime
Paper 1Simple familiar, multiple choice and short response30%90 min + 5 min perusal
Paper 2Complex familiar and complex unfamiliar, short response20%90 min + 5 min perusal

Source: QCAA General Mathematics syllabus and QCAA external assessment timetable. Last checked: 18 November 2026.

On the 2025 papers, Paper 1 was worth 57 marks and Paper 2 was worth 38, according to the QCAA marking guide. That works out at about 1.6 minutes a mark on Paper 1 and 2.4 minutes a mark on Paper 2. Paper 2 gives you more time per mark because each question needs more thinking before you write.

To see how the exam counts towards your result, read how external exams count towards your QCE and ATAR.

Using QCAA past papers written before the 2025 syllabus

The 2025 syllabus applies to students completing Units 3 and 4 from 2026. That means the QCAA papers from 2020 to 2025 were set on the earlier 2019 syllabus. Many of their regression, annuity and network questions still match what you study now, so they are well worth doing. Check each question's topic against the current syllabus before you count it as revision. Our guide to QCE past papers shows where to find them and how to mark your own answers.

The answers below follow mark schemes written the way exam markers award marks. Two abbreviations are worth knowing. "cao" means correct answer only. "ft" means follow through: if an earlier value is wrong but you use it correctly in the next step, you can still earn that step's mark. Follow-through marks only exist if your working is on the page.

Bivariate data practice question: regression with marks shown

Medly's lesson on least-squares equations teaches the line in a fixed order: slope first, then intercept, then the equation. The ideas you need are:

  • The least-squares line is y = mx + c, where x is the explanatory variable and y is the response variable.
  • The slope is m = r × sᵧ ÷ sₓ, measured in y-units per x-unit. It has the same sign as r.
  • The intercept is c = ȳ − m × x̄, measured in y-units.
  • The line always passes through the mean point (x̄, ȳ), so substituting x̄ should give ȳ. That is a quick check on your equation.

This question from Medly asks you to choose between two explanatory variables first, which is typical of a longer question.

Question 1: (5 marks)

In a community garden, pollinating-insect visits are linked to mean daily sunlight hours. The number of weekly visits is also linked to irrigation sessions. For six weeks, observations record visits with both factors. The target week has 6 sunlight hours and 4 irrigation sessions.

Weekx₁ sunlight hoursx₂ irrigation sessionsy insect visits
12113
23617
34220
45525
56328
67432

Calculate, using technology, the correlation coefficient for each pairing of y with x₁ and x₂; identify the explanatory variable with the stronger linear association; determine its least-squares equation and use it to predict the number of pollinating-insect visits in the target week as a whole number.

Answer
  1. Enter the pairs into your calculator's statistics mode, keeping each week's values in the same row. This gives r(x₁, y) ≈ 0.998 and r(x₂, y) ≈ 0.293. 1 mark for both values.
  2. Sunlight hours, x₁, has the stronger linear association, because 0.998 is much closer to 1 than 0.293. 1 mark.
  3. Linear regression of y on x₁ gives m = 3.8 and c = 5.4, so the least-squares equation is y = 3.8x + 5.4. 1 mark.
  4. The target week has 6 sunlight hours, so substitute x = 6: y = 3.8(6) + 5.4. 1 mark.
  5. y = 22.8 + 5.4 = 28.2, so the prediction is 28 visits. 1 mark, needed for full marks.

Check: x̄ = 4.5 and ȳ = 22.5. Substituting gives 3.8 × 4.5 + 5.4 = 17.1 + 5.4 = 22.5, so the line passes through the mean point.

The most common slip is substituting the 4 irrigation sessions instead of the 6 sunlight hours. Underline which variable your equation uses before you substitute.

Loans, annuities and investments practice question: recurrence relations

A reducing balance loan is an ordinary annuity: interest is added for the period first, then the repayment comes off. Medly's lesson on present-value annuities models it two ways.

  • The recurrence relation Aₙ₊₁ = rAₙ − d, where r = 1 + i, i is the interest rate per period and d is the repayment. Use it when you need the balance after a few periods.
  • The present value formula A = d × (1 − (1 + i)⁻ⁿ) ÷ i. Use it when you need the starting amount or the repayment directly.
  • In both, i and n must match the payment period. Monthly repayments need a monthly rate, and n counts months.

Question 2: (6 marks)

A cinema secures a reducing-balance loan with an initial principal of $18,000. The loan accrues interest at an annual rate of 6.0%, compounded monthly, and scheduled repayments of $370 are made at the end of each month.

(a) Write a recurrence relation for the loan balance after n months. (2 marks)

(b) Calculate the loan balance after two months. (1 mark)

(c) Determine the total interest charged across the two months by comparing the overall repayments made during this period with the net reduction in the loan balance. (3 marks)

Answer

Part (a)

  1. Monthly interest rate: i = 0.06 ÷ 12 = 0.005. 1 mark.
  2. Interest multiplier: r = 1 + i = 1.005. 1 mark.
  3. A₀ = 18,000 and Aₙ₊₁ = 1.005Aₙ − 370. 1 mark, needed for full marks.

Part (a) is capped at 2 marks, but you only get both if the complete relation, with the starting balance, is written down.

Part (b)

  1. A₁ = 1.005 × 18,000 − 370 = 18,090 − 370 = 17,720.
  2. A₂ = 1.005 × 17,720 − 370 = 17,808.60 − 370 = $17,438.60. 1 mark.

Part (c)

  1. Reduction in the balance: 18,000 − 17,438.60 = $561.40. 1 mark (ft from your A₂).
  2. Total repayments: 2 × 370 = $740. 1 mark.
  3. Interest: 740 − 561.40 = $178.60. 1 mark, needed for full marks.

Check: month 1 interest is 0.005 × 18,000 = $90 and month 2 interest is 0.005 × 17,720 = $88.60. Together that is $178.60.

Marks are often lost by using 0.06 as the monthly rate. Convert the rate before you write the recurrence.

Networks and decision mathematics practice question: critical path

Critical path analysis tells you which activities control a project's finish date. From Medly's lesson on critical paths:

  • An activity's EST (earliest start time) comes from a forward scan: take the largest finish time of everything before it.
  • Its LST (latest start time) comes from a backward scan: the latest it can start without delaying the project.
  • Float = LST − EST. A critical activity has EST = LST and zero float.
  • The critical path is a continuous start-to-finish chain of critical activities, and its total duration is the minimum completion time.

Question 3: (5 marks)

A community garden is being installed. The activities are listed below.

ActivityTaskDuration (days)Immediate predecessor(s)
Aprepare site2start
Border materials4A
Crecruit volunteers3A
Dbuild garden beds5B
Econduct safety induction2C
Fplant seedlings3D, E

Draw the complete project network diagram, showing all activities, durations and precedence relationships. Use forward and backward scanning to determine EST(E), EST(F) and LST(E). Classify activity E as critical or non-critical, calculate its float time, and state the greatest delay activity E can have without delaying the project.

Answer
A, 2 B, 4 C, 3 D, 5 E, 2 F, 3 0 / 0 2 / 2 6 / 6 5 / 9 11 / 11 14 / 14
Diagram not drawn accurately

Each pair next to a node is the earliest / latest event time, in days.

  1. Draw the network: A from the start, B and C both after A, D after B, E after C, and F after both D and E. 1 mark for a valid network, 1 mark for every activity labelled with its duration.
  2. Forward scan: EST(A) = 0 and EST(B) = EST(C) = 2. EST(D) = 2 + 4 = 6 and EST(E) = 2 + 3 = 5.
  3. EST(F) is the larger of 6 + 5 = 11 and 5 + 2 = 7, so EST(F) = 11. 1 mark for EST(E) = 5 days and EST(F) = 11 days.
  4. Backward scan: the project finishes at 11 + 3 = 14 days, so LST(F) = 11 and LST(E) = 11 − 2 = 9 days. 1 mark.
  5. EST(E) = 5 and LST(E) = 9 are not equal, so E is non-critical. 1 mark.
  6. Float of E = LST − EST = 9 − 5. 1 mark.
  7. Float = 4 days, so E can be delayed by up to 4 days without delaying the project. 1 mark, needed for full marks.

There are seven marking points, capped at 5. The critical path is A → B → D → F, with a minimum completion time of 2 + 4 + 5 + 3 = 14 days.

In the forward scan, a node where two activities meet takes the larger finish time. Taking the smaller one (7 here) is where most marks go.

QCE General Mathematics practice questions with answers

These five are Medly questions, from Medly's lessons and practice papers. The first three are closer to Paper 1. The last two need more steps, the way Paper 2 questions do.

Question 4: (4 marks)

For a coffee-roasting quality study, roasting time, x, is measured in minutes and sensory-quality score, y, is measured in quality points. The summary statistics are r = 0.84, sₓ = 2.5 minutes and sᵧ = 6.0 quality points. Determine the slope of the least-squares line, giving suitable units.

Answer
  1. Use the slope rule m = r × sᵧ ÷ sₓ. 1 mark.
  2. Substitute: m = 0.84 × 6.0 ÷ 2.5. 1 mark.
  3. m = 5.04 ÷ 2.5 = 2.016, or 2.02 to 2 decimal places. 1 mark.
  4. Units: quality points per minute. 1 mark.

This is from one of Medly's practice papers (paper C, Paper 1). The units mark is easy to miss: always y-units per x-unit.

Question 5: (3 marks)

A credit-union loan has 36 equal end-of-month payments of $400 at 0.5% monthly interest.

(a) What is the present value of the loan to the nearest cent? (1 mark)

(b) Determine the total repayments made to complete the loan. (1 mark)

(c) What is the total interest paid on the loan to the nearest cent? (1 mark)

Answer
  1. Use A = d × (1 − (1 + i)⁻ⁿ) ÷ i with d = 400, i = 0.005 and n = 36.
  2. A = 400 × (1 − 1.005⁻³⁶) ÷ 0.005 = $13,148.41. 1 mark.
  3. Total repayments: 36 × 400 = $14,400. 1 mark.
  4. Total interest: 14,400 − 13,148.41 = $1,251.59. 1 mark.

This is from one of Medly's practice papers (paper A, Paper 1).

Question 6: (2 marks)

An accessible playground project has the following activities. The listed EST and LST values have been found by scanning the project network.

ActivityDaysPredecessor(s)EST / LST
A: survey site2start0 / 0
B: obtain permit5A2 / 2
C: hire team5A2 / 2
D: install equipment4B7 / 7
E: deliver safety surfacing4C7 / 7
F: final inspection1D, E11 / 11

Determine the critical activities and completion time for the accessible playground project.

Answer
  1. Every activity has EST = LST, so A, B, C, D, E and F are all critical. 1 mark (all six needed).
  2. There are two critical paths, A → B → D → F and A → C → E → F, each lasting 2 + 5 + 4 + 1 = 12 days.
  3. The minimum completion time is 12 days. 1 mark.

The answer "12" with no unit doesn't earn the second mark. Write "12 days".

Question 7: (6 marks)

Researchers model y, the full-charge battery capacity in minutes, from x, the battery age in months. The least-squares model has the form y = mx + c. For a set of batteries, x̄ = 30 months, ȳ = 480 minutes, sₓ = 5 months, sᵧ = 60 minutes and r = −0.70. A residual is the actual capacity minus the fitted capacity. At x = 38 months, the residual is −7 minutes.

Determine the actual full-charge battery capacity at 38 months, to the nearest whole number.

Answer
  1. Substitute into the slope rule: m = (−0.70) × 60 ÷ 5. 1 mark.
  2. m = −42 ÷ 5 = −8.4 minutes per month. 1 mark.
  3. c = ȳ − m × x̄ = 480 − (−8.4)(30) = 480 + 252 = 732. 1 mark.
  4. Fitted capacity at 38 months: y = −8.4(38) + 732 = −319.2 + 732 = 412.8 minutes. 1 mark.
  5. Actual = fitted + residual = 412.8 + (−7) = 405.8, so 406 minutes. 1 mark.
  6. 1 mark for setting out the slope, intercept, prediction and residual correction in a clear, logical order.

A residual is actual minus fitted, so the actual value is fitted plus residual. Adding 7 instead of subtracting it gives 420 and loses the final mark.

Question 8: (5 marks)

A retiree has $320,000 immediately before monthly withdrawals begin. The account earns a fixed annual interest rate of 4.8% p.a., compounded monthly, for 15 years. Withdrawals are made at the end of each month. An adviser claims that the interest contribution to the withdrawals will exceed $130,000.

Evaluate the reasonableness of the adviser's claim that the interest contribution will exceed $130,000.

Answer
  1. Align the rate and periods: i = 0.048 ÷ 12 = 0.004 and n = 15 × 12 = 180. 1 mark (both needed).
  2. Solve 320,000 = d × (1 − 1.004⁻¹⁸⁰) ÷ 0.004 for the withdrawal: d ≈ $2,497.33. 1 mark.
  3. Total withdrawals: 180 × 2,497.33 ≈ $449,519.40. 1 mark.
  4. Interest contribution: 449,519.40 − 320,000 = $129,519.40. 1 mark.
  5. $129,519.40 is less than $130,000, by about $481, so the adviser's claim is not reasonable. 1 mark.

The last mark needs a conclusion that answers the claim. A correct number with no verdict stops at 4 out of 5.

To practise more questions like these, Medly's QCE General Mathematics course has exam-style questions for each lesson in Units 3 and 4, marked against a mark scheme so you can see which step earned or lost each mark. Medly's free plan includes 5 marked questions and 20 AI tutor messages a day, with no card needed. If you're planning the weeks before the exam, our 8-week plan fits General Mathematics around your other subjects.

Frequently asked questions

How long is the QCE General Mathematics external exam?

There are two papers. Each gives you 90 minutes of working time plus 5 minutes of perusal, and they are sat in separate sessions.

Can I use a calculator in both papers?

Yes. You can use a handheld QCAA-approved scientific calculator in both papers, but not a graphics calculator. The QCAA formula book is provided.

How much is the General Mathematics external exam worth?

It is worth 50% of your subject result. Under the 2025 syllabus, Paper 1 carries 30% and Paper 2 carries 20%.

Are QCAA past papers from before 2026 still useful?

Yes. Papers from 2020 to 2025 were set on the 2019 syllabus, but many questions on regression, annuities and networks still match current content. Check each topic against the 2025 syllabus as you go.

What does "ft" mean on a marking guide?

It means follow through. If you make an error early but use your wrong value correctly later, you can still earn the later marks, as long as your working is shown.